TheFeature Fireplace and a New Doorway

  • Arnsheen
  • Dec 2, 2021
  • 1 min read

ree

ree


In June 2020 the first of two new architectural features was added to the building.This was a doorway opening from the first floor in the tower, into what is will be the Master bedroom. The second was the large fireplace on what used to be the pulpit and altar end wall of the nave. The other side of this wall will eventually be a main inner wall of the kitchen.


ree
Unloading the cut granter from the pickup truck

ree

ree
A concrete base 8" deep was prepared,


ree

ready to set the granite hearth on to the concrete base

\


ree

The opening that was made for plant to gain access inside the building was first filled in to add support to the main wall and then supports were used to hold up the building end wall whilst the fireplace cavity was knocked through.

ree

ree


ree
rear wall of fireplace blocked in with 4 holes for water pipes going in and out of the multi fuel stove

ree
using recycled bricks from underneath the original floor in the nave, a herringbone pattern was laid out for the masons to set into the back and sides of the fireplace


ree
getting ready to place the oak mantelpiece

finished!

perspective shot 😊

 
 
 

1 Comment


jimmycurtin
Dec 02, 2021

Beautiful work Rod. You should be very proud.